Groundworks method statement template: plan the excavation before the dig
A groundworks method statement should describe the actual site's sequence from surveys and buried-service checks through excavation, protection, inspection, work in the trench and safe backfill. The copyable form below records the decisions and hold points that a supervisor must complete. It is for Great Britain and does not authorise a specific excavation, select a trench-support system or replace a permit, temporary-works design or risk assessment.
HSE's HSG47 guidance frames a safe approach to underground services as planning the work, locating and identifying services, and safe excavation. HSE's excavation guidance warns that ground cannot be assumed to stand unsupported. Those principles must be translated into the real ground conditions, depth, adjacent structures, people, plant and utilities at the site. The existing Complys groundworks RAMS guide owns the explanatory intent. This proposed route is a reusable form for a defined job; merge it with a dedicated existing template if repository review finds one.
Decide the scope and controls first
Before work, obtain drawings and service information from the client and relevant asset owners; consult the project design, ground investigation, temporary-works arrangements and construction-phase plan. Plans are indicators, not guarantees of exact service position. HSE says competent people should use suitable locating devices, identify and mark services, and repeat locating during work. A signed “plans checked” box is not permission to machine dig over a possible live cable.
Decide how collapse will be prevented and how people will enter and leave safely. The competent person must assess whether support, battering or another method is appropriate; there is no universally safe unsupported depth. Consider adjacent foundations, roads, vehicles, spoil and materials near the edge, water, weather and vibration. Protect against people or plant falling in. Make the needed support and barriers available before excavation starts. If a service is struck, a side moves, water enters or a previously unknown structure appears, stop and reassess.
Copyable groundworks method statement
A. Document control and exact task
| Field | Complete for this excavation |
|---|---|
| Project, client, address and work-area coordinates/drawing | [ ] |
| Principal contractor, groundworks contractor and supervisor | [ ] |
| Task, intended dimensions and purpose | [ ] |
| Start/end date, shift, version and approval | [ ] |
| Ground information and adjacent structures | [ ] |
| Buried-service plans, owners, dates and limitations | [ ] |
| Locator operator, equipment and records | [ ] |
| Temporary-works design/support reference and responsible person | [ ] |
| Dig permit, isolation and other authorisations | [ ] |
| Risk assessment, construction-phase plan and interfaces | [ ] |
| Emergency plan, service-owner contacts and site access | [ ] |
| Work excluded from this method | [ ] |
Stop-work authority: [role/name]. Change approval: [role/name]. State who can redesign support, revise a dig permit or approve a different excavation method. The excavator operator should not make a structural design decision because the crew has already arrived.
B. Pre-start hold points
| Hold point | Evidence / result | Released by |
|---|---|---|
| Drawings and service plans obtained and reviewed | [ ] | [ ] |
| Site walkover and surface clues considered | [ ] | [ ] |
| Services located, marked and uncertainty recorded | [ ] | [ ] |
| Required isolations or asset-owner advice confirmed | [ ] | [ ] |
| Ground, depth and adjacent load assessment completed | [ ] | [ ] |
| Support/battering and edge protection specified and available | [ ] | [ ] |
| Plant route and pedestrian exclusion agreed | [ ] | [ ] |
| Spoil, materials and vehicle loading kept to assessed positions | [ ] | [ ] |
| Access/egress and water control ready | [ ] | [ ] |
| Permit, briefing and emergency response complete | [ ] | [ ] |
Do not release digging if buried-service information is missing or inconsistent, the locating result conflicts with the plan, support is unavailable, or an adjacent foundation could be undermined without a competent solution. HSE notes that even a small trench can undermine a shallow boundary wall. Document how uncertainty is resolved; do not replace it with an arbitrary clearance distance copied from a generic form.
C. People, equipment and site controls
| Element | Job-specific entry |
|---|---|
| Supervisor, excavator operator, banksman and locator operator | [ ] |
| Competence and brief records | [ ] |
| Excavator, attachment, inspection and exclusion area | [ ] |
| Service-locating equipment, calibration/check and method | [ ] |
| Hand tools, insulated tools where appropriate and trial-hole method | [ ] |
| Support, trench box, battering or temporary-works reference | [ ] |
| Barriers, crossing points and public protection | [ ] |
| Safe access, egress and rescue arrangement | [ ] |
| Spoil position, plant set-back and material delivery route | [ ] |
| Water, weather and contamination controls | [ ] |
Where lifting equipment is used, plan the lift under the relevant lifting requirements; this form does not constitute a lift plan. Where excavation may be a confined space, obtain a competent assessment and the separate controls that apply. Do not automatically label every trench a confined space, or assume none can be one. Check ground contamination, dust and waste hazards against the actual site assessment.
D. Work sequence and control record
| Step | Site-specific method | Control and record |
|---|---|---|
| 1. Set out and isolate area | [Confirm lines, working space, barriers, traffic and pedestrian route.] | [Check drawing version and site interfaces.] |
| 2. Locate services | [Review plans, scan, mark and record uncertainty.] | [Competent operator, repeat scans as work progresses.] |
| 3. Trial and expose | [Describe safe hand-dig/trial-hole method near services.] | [No assumed location from plans alone; stop on discrepancy.] |
| 4. Establish support and edge controls | [Install planned support/battering and barriers in the designed sequence.] | [Competent check before anyone enters.] |
| 5. Excavate | [State plant, direction, increments, banksman and spoil route.] | [Segregate people/plant; control side loads, water and services.] |
| 6. Inspect | [State who checks after opening and when conditions change.] | [Record findings and corrective actions before entry/restart.] |
| 7. Work within excavation | [Describe pipe, foundation or other actual task.] | [Maintain support/access; watch for services and movement.] |
| 8. Backfill and reinstate | [Protect services, inspect work, place fill and compact as specified.] | [Do not damage services or remove support out of sequence.] |
| 9. Handover | [Clear plant, barriers as appropriate, waste and permit.] | [Record as-built/service changes and client acceptance.] |
HSE's underground-service guidance says plans give only an indication, locating equipment has limits and careful excavation is essential. It describes trial holes using suitable hand tools as necessary and safe practices near cables. The exact method must be chosen for the service type and site. Do not turn the table into “mechanical excavation until a fixed distance” without competent and asset-owner support.
E. Inspection, change and emergency controls
| Trigger | Immediate action and decision owner |
|---|---|
| Unknown cable, pipe, duct or obstruction | [Stop; protect area; identify and consult owner/competent person.] |
| Cable/pipe strike or suspected damage | [Stop; keep people clear; contact emergency/asset owner under site plan.] |
| Side movement, cracking, falling material or support damage | [Stop entry; evacuate safely; competent reassessment/design.] |
| Heavy rain, groundwater or flooding | [Stop if controls fail; reassess stability and electrical/service risk.] |
| Plant encroaches on edge or barrier fails | [Stop plant; restore exclusion and assess ground loading.] |
| Adjacent structure shows movement | [Stop; make area safe; obtain competent structural advice.] |
| Emergency involving person in excavation | [Follow site rescue plan; do not create a second casualty.] |
HSE says excavations need inspection and appropriate precautions against collapse, falling material and falls. Record the inspection regime required by the project and law; do not invent a single calendar frequency that fits every changing condition. An excavation that was safe at the start of a shift may need reassessment after rain, support movement or an altered load. Train the team to report warning signs promptly.
F. Briefing, revision and handover
| Person | Role | Current method briefed? | Questions/changes | Signature/date |
|---|---|---|---|---|
| [ ] | Supervisor | [ ] | [ ] | [ ] |
| [ ] | Plant operator | [ ] | [ ] | [ ] |
| [ ] | Banksman/locator | [ ] | [ ] | [ ] |
| [ ] | Other operative | [ ] | [ ] | [ ] |
| [ ] | Site representative | [ ] | [ ] | [ ] |
Replace superseded copies. Before each restart, compare actual ground, weather, services, plant and support against the method. The person approving a change should record what changed, why the revised control is adequate and how everyone was re-briefed. Signatures show communication, not that the excavation is automatically safe.
Worked example: drainage trench near a boundary wall
A contractor plans a drainage trench next to an older brick boundary wall. The drawing shows a sewer but service records are incomplete, and the wall's foundation depth is unknown. The template exposes two unresolved hold points: service location and structural support. The supervisor does not permit excavation while a locator is absent or assume the wall can stand beside an open trench. The project obtains service information, locates and confirms lines using a competent method, and seeks competent advice on excavation support and the wall. The work sequence, spoil position and plant route are revised to match those decisions. This scenario illustrates why the form is a gate, not a substitute for engineering judgement.
Common failures to remove from a generic form
- “Services checked” with no plan version, locator evidence or uncertainty.
- A fixed “safe depth” for unsupported sides despite changing ground and loads.
- Spoil, excavator or vehicles loaded close to an unassessed edge.
- “Banksman in place” while pedestrians can still enter the plant zone.
- No safe access/egress or rescue plan for workers in the excavation.
- Temporary support listed but not on site before digging.
- Backfilling without protecting and recording exposed services.
- Continuing after a new service, wall movement or water ingress without revision.
The Complys groundworks RAMS guide explains the hazard context. The generic method statement template covers other activities, while the RAMS product page is the commercial next step for project-specific document creation. Verify the current implementation and trial terms before making product claims. A generated document cannot locate a cable, design trench support or approve a dig permit. Complete this form with a competent team, obtain required authorisations and inspect the controls on site.
Source, claim, owner, product, links and writer-side QA
| Check | Evidence / decision |
|---|---|
| Primary sources | HSE HSG47; HSE excavation safety; HSE electrical service excavation guidance; HSE construction method statements. Checked 5 October 2026. |
| Claim register | HSG47 three-part approach, limits of service plans, competent locating/repeated scans, safe excavation; collapse support and edge/adjacent-structure precautions. No fixed safe unsupported depth or assumed service clearance. |
| Owner/cannibalisation | Existing .co.uk groundworks RAMS blog owns explainer intent; generic method template owns cross-trade form. Proposed route owns copyable groundworks-specific sequence and hold points. No exact live form observed; check repository/unpublished owner and MERGE if present. |
| Product truth | RAMS product page observed; no claim the software issues a dig permit, locates services or designs support. Implementation and terms require check. |
| Internal links | Verified groundworks RAMS explainer, generic method template and RAMS money page plus HSE primary sources. |
| QA | Direct answer, usable form, pre-start gates, sequence, change/emergency response, example, metadata and CTA. Writer-side READY only; competent site-specific and independent legal/construction QA remain. |