Landscaping method statement template
A landscaping method statement should set out what will be changed on the site, how workers will prepare and protect the area, the sequence of ground and planting work, the equipment used, and the controls for buried services, people, machinery and materials. This copyable Great Britain template can support soft landscaping, minor hard-landscaping interfaces and grounds projects after a task-specific risk assessment. It is not a permit to dig or a universal tree-surgery or pesticide application method.
The Complys generic method statement template covers the basic cross-trade sequence. Landscaping needs its own survey and ground-contact decisions: a bed excavation can strike a shallow cable; a delivery vehicle can conflict with the public; a tree-planting operation can require handling aids. The final method must match the design, terrain, season, weather, ground conditions and who uses the site while work proceeds.
Define the actual landscaping package
List each operation: site clearance, stripping turf, minor excavation, drainage, edging, paving, soil import, planting, mulching, irrigation or maintenance. Separate tasks with different hazard profiles. A plan for hand planting low shrubs is not sufficient for excavating a trench, operating a mini-excavator, applying a professional-use pesticide or cutting a tree with a chainsaw. Name specialist contractors and their own documentation where those tasks fall outside the core landscaping team.
Before any excavation, HSE's HSG47 sets out the three parts of a safe system near underground services: plan the work, locate and identify services, then excavate safely. Drawings alone may not show private or moved services. Record what information was obtained, the detection method, who used it and the safe digging technique. HSE's excavation guidance also calls for ground, collapse, access, water and adjacent-structure risks to be controlled where relevant. A shallow planting hole can still contact a service; a deep trench needs a separately competent temporary-support and inspection plan.
Copyable landscaping method statement
Replace every bracket with an actual decision. Delete branches that do not apply, and add a separate specialist method for excluded higher-risk tasks.
A. Project and task details
| Field | Complete for this site |
|---|---|
| Client, site address, GB nation and exact work zone | [ ] |
| Contractor, supervisor, author, reviewer, version and date | [ ] |
| Landscape drawings, levels, specification and revision | [ ] |
| Work package: soft landscape, paving, drainage, irrigation, maintenance | [ ] |
| Existing trees, structures, paths, play areas, traffic and public use | [ ] |
| Working hours, deliveries, storage and access route | [ ] |
| Ground conditions, slope, water and forecast/weather limits | [ ] |
| Utility plans, locator survey and permit-to-dig reference | [ ] |
| Plant/material schedule, soil source and waste route | [ ] |
| Specialist works excluded and separate method owner | [ ] |
| Risk assessment, COSHH, emergency contact and first aid | [ ] |
| Stop-work authority and change approver | [ ] |
The work zone must be drawn or described so crews can distinguish a planting bed from a service corridor, protected tree roots and a public path. Check planning/design constraints, ecology and site permissions where relevant; a method statement should reference the appointed designer or client approval rather than inventing a universal environmental rule.
B. Pre-start survey and hold points
| Hold point | Evidence/result | Released by |
|---|---|---|
| Boundaries, drawings and existing levels verified | [ ] | [ ] |
| Buried and overhead services information obtained and marked | [ ] | [ ] |
| Locator operator/limitations and trial-hole plan agreed | [ ] | [ ] |
| Excavation support, edge, access and water controls assessed | [ ] | [ ] |
| Existing trees/root protection and ecological constraints understood | [ ] | [ ] |
| Public, occupant and vehicle segregation installed | [ ] | [ ] |
| Plant/vehicle route, ground bearing and turning area checked | [ ] | [ ] |
| Manual handling and mechanised delivery aids available | [ ] | [ ] |
| Tools, guards and operator competence confirmed | [ ] | [ ] |
| Soil, plant and chemical product information reviewed | [ ] | [ ] |
| Emergency route, service owner contacts and spill response known | [ ] | [ ] |
Do not release ground breaking because someone says “there should be no services here”. HSE's underground-cable guidance recommends plans, suitable locating equipment and safe digging, with competent users who understand the locator's limits. Where a service is suspected or found, review the excavation method and communicate the marked route. HSG47 is a decision framework; it does not let this generic form specify one fixed clearance distance for every utility and situation.
C. Workers, plant and protective measures
| Item | Site-specific entry |
|---|---|
| Crew, supervisor and machine operators | [ ] |
| Excavator, dumper, compactor, mower, brush-cutter or hand tools | [ ] |
| Machinery inspection, guarding, keys and exclusion zones | [ ] |
| Reversing/traffic plan and banksman where assessed | [ ] |
| Soil, plants, slabs and bags: weight, delivery and handling aid | [ ] |
| Dust, noise and vibration assessment/control | [ ] |
| Chemical product label/SDS and COSHH assessment | [ ] |
| Task-specific head, eye, hand, foot, hearing and respiratory protection | [ ] |
| Barriers/signage for pedestrians, residents and children | [ ] |
| Washing, welfare, weather and heat/cold arrangements | [ ] |
HSE's planting advice identifies handling, cuts and moving machinery and recommends arranging deliveries to reduce carrying. Design the route and work order so pallets or plants are deposited near their final location where practicable. Assess the actual loads and ground; do not turn “team lift” into a substitute for a suitable mechanical aid.
If professional-use plant protection products are in scope, the contractor needs a separate product, label, training/certification and environmental-control decision. HSE's pesticide FAQ says professional-use products require the specified competence route; a generic landscape form should not claim every worker can spray. The safest choice may be to omit chemical treatment altogether. Record this as a separate specialist work package rather than a line reading “spray weeds as required”. Likewise, HSE requires adequate task-specific chainsaw training and competence; tree work, particularly aerial work, needs its own competent plan.
D. Planned sequence
| Step | Describe the actual method | Control/evidence |
|---|---|---|
| 1. Brief and set boundaries | [Confirm design, utility plan, roles, public route and stop points.] | [Briefing log; barriers; permits.] |
| 2. Survey and locate | [Mark services, roots, structures, levels and access constraints.] | [Locator/trial-hole evidence; release to dig.] |
| 3. Deliver and stage | [Unload soil, plants and materials using assessed route.] | [Separate people/vehicles; stable storage.] |
| 4. Clear existing surface | [State vegetation, turf or debris removal and segregation.] | [Sharps/unknown-material stop point; dust control.] |
| 5. Excavate or prepare ground | [State depth, machinery, safe dig, support and spoil placement.] | [Service/edge/collapse controls; competent checks.] |
| 6. Install bases or drainage | [Follow approved detail and connect only authorised systems.] | [Inspection before backfill or concealment.] |
| 7. Place soil, edging or paving | [Set levels, compact/fix per design, maintain access.] | [Handling and plant/public separation.] |
| 8. Plant and mulch | [Prepare holes, move stock, plant, water and protect.] | [Root/utility controls; plant condition record.] |
| 9. Test and inspect | [Check drainage/irrigation, levels, stability and finish.] | [Defect and hold-point records.] |
| 10. Reinstate and hand over | [Remove waste/plant, open paths, provide care schedule.] | [Client inspection, maintenance and restrictions.] |
This is a sequence to customise, not an instruction to do all ten stages. Paving, drainage and tree planting may each need detailed drawings and separate inspection points. If a design changes after excavation, stop that portion and obtain approval before backfill. Photograph a buried drain or service crossing before it is concealed, where the contract calls for such evidence.
E. Stop-work and change decisions
| Trigger | Immediate action and restart owner |
|---|---|
| Unidentified cable/pipe, marker tape or unexpected chamber | [Stop digging; protect area; utility owner/competent review.] |
| Ground instability, water ingress or unsupported edge | [Stop access; competent excavation reassessment.] |
| Machinery/public segregation fails | [Stop machine; restore exclusion/traffic control.] |
| Possible contaminated soil or sharps | [Stop affected handling; competent assessment and disposal route.] |
| Protected root/design boundary differs from plan | [Stop affected work; designer/client decision.] |
| Unplanned tree cutting, pesticide use or deep excavation | [Do not improvise; separate competent method and approval.] |
| Weather makes slopes, lifting or equipment unsafe | [Stop; revise sequence and access.] |
| Plant/material substitution | [Confirm design and care requirements before use.] |
Record the location, time, who was told, the revised plan and who briefed the crew. If a service is damaged, keep people clear and follow the site emergency procedure and service-owner advice. Do not attempt an unqualified repair or cover the damage before reporting it.
F. Briefing and handover record
| Person/role | Method version | Question/change | Sign/date |
|---|---|---|---|
| [ ] | [ ] | [ ] | [ ] |
| [ ] | [ ] | [ ] | [ ] |
| [ ] | [ ] | [ ] | [ ] |
| Handover item | Evidence and recipient |
|---|---|
| Final levels, drainage and concealed work inspections | [ ] |
| Plant species, locations and condition | [ ] |
| Irrigation settings, isolation and maintenance instructions | [ ] |
| Waste removal and public path reinstatement | [ ] |
| Defects, establishment period and watering/aftercare owner | [ ] |
| As-built/service amendments and client acceptance | [ ] |
The final client handover should say what is complete, what remains restricted, who maintains planting during establishment and what evidence supports buried or concealed work. A green appearance on day one does not prove drainage, service clearance or future plant survival.
Example: planting beside a public footpath
A contractor is asked to replace a grass strip with shrubs and edging beside a busy path. The survey shows a lighting column and a possible cable route. Before digging, the supervisor requests service information, arranges competent locating and marks the likely route. Pedestrians are redirected behind a suitable barrier; deliveries are scheduled when the path can be controlled. Plants and soil are placed near the work zone to reduce carrying. The crew hand-digs trial holes where the safe-dig plan requires them. When an unexpected duct appears, excavation stops until its identity and a safe method are confirmed. The team then completes approved edging and planting, checks final levels, reopens the path only after clearing tools and trip hazards, and hands over watering responsibilities. This example shows decisions, not a ready-made permit for that site.
Frequent template errors
- Treating a planting plan as proof that there are no underground services.
- Using an excavation method without ground, support, water and access decisions.
- Allowing a mower, dumper or excavator to operate beside an unsegregated public path.
- Carrying heavy soil bags across the site because delivery location was not planned.
- Adding chainsaw work or professional pesticide application as an informal extra task.
- Working around protected roots or structures without the approved design boundary.
- Backfilling a changed drain or service crossing without an inspection record.
- Handing over plants with no agreed establishment or watering owner.
The Complys RAMS page covers a site-specific document workflow. A system can help arrange a document; it cannot locate a cable, certify pesticide competence or approve an excavation. Complete the site method with competent people and verify controls on the ground.