Painting and decorating method statement template
A painting and decorating method statement should set out how the team will survey existing surfaces, protect people and property, prepare the substrate, control dust and chemicals, apply the specified system, check the finish and hand over the work. Use this Great Britain form after a task-specific risk assessment. It is adaptable to brush and roller work on domestic or commercial refurbishment; old lead paint, asbestos-containing materials, spray coatings or work at height need explicit specialist decisions rather than assumptions.
The live Complys general method statement template covers the cross-trade sequence. This page is distinct because a decorator must decide what the existing coating is, whether disturbing it creates harmful dust or fume, what the product safety data requires and whether occupants can remain nearby. It is not a universal paint specification. The designer/client and product manufacturer determine substrate preparation, compatible primer, application conditions and finish acceptance.
Confirm the scope and surface before work starts
Record each surface, room, building age, existing finish, proposed coating, preparation method and access equipment. A “repaint walls” instruction may hide old paint layers, damp, damaged plaster or a surface that forms part of a fire-protected assembly. If the substrate is unsound or the coating is incompatible, obtain an approved repair or product decision before covering it. Do not treat painting over a defect as repairing it.
HSE notes that painting work can involve sanding, filling and spraying with exposure to lead, solvents, construction dust, asbestos and other hazardous substances. HSE's lead guidance particularly flags old coatings in pre-1980s buildings and dry sanding or burning paint. Review available building information and seek competent advice before disturbing suspect lead or asbestos. This general form does not authorise lead stripping, asbestos work or specialist spraying. A new product may also introduce solvent, isocyanate or other hazards, so read the label and safety data and complete the appropriate assessment.
Copyable painting and decorating method statement
Replace brackets with the actual job. Remove non-applicable stages and attach the product system, COSHH and access plans where required.
A. Job details and documents
| Field | Complete for this project |
|---|---|
| Client, site, room/area and GB nation | [ ] |
| Contractor, supervisor, author, date and document version | [ ] |
| Surface/substrate and existing coating information | [ ] |
| Work scope: protection, removal, repair, preparation, application, finish | [ ] |
| Product names, manufacturer instructions, batch and SDS | [ ] |
| Colours, finish, number of coats and acceptance specification | [ ] |
| Risk assessment, COSHH, lead/asbestos information and permits | [ ] |
| Occupancy, other trades and ventilation arrangements | [ ] |
| Access equipment and work-at-height assessment | [ ] |
| Excluded specialist work, stop authority and emergency contact | [ ] |
Decide whether the work can be done while a building is occupied. If solvents or sanding dust may spread into adjacent rooms, agree segregation, ventilation and the sequence with the client. The exact arrangement should respect fire escape and welfare access. A signed method with no room-by-room staging plan will not tell workers when an area can be reopened.
B. Pre-start release points
| Hold point | Evidence/result | Approver |
|---|---|---|
| Surface condition and moisture/defect issues inspected | [ ] | [ ] |
| Old coating and building-material hazards assessed | [ ] | [ ] |
| Lead/asbestos decision and any specialist method available | [ ] | [ ] |
| Product system and substrate compatibility confirmed | [ ] | [ ] |
| COSHH/SDS, ventilation and skin/eye/respiratory controls agreed | [ ] | [ ] |
| Occupant/other-trade protection and access route ready | [ ] | [ ] |
| Ladder, tower or platform selection and inspection complete | [ ] | [ ] |
| Fire sources, storage and spill/waste arrangements checked | [ ] | [ ] |
| Inspection, drying/recoat and handover conditions agreed | [ ] | [ ] |
Old coating uncertainty is a real stop point. HSE's old lead paint sheet advises planning to avoid unnecessary stripping and controlling dust and fume where removal is needed. A project may also require an asbestos survey or register before disturbing old textured coating, lining or other material. Do not choose dry sanding merely because it is fast. The correct process depends on identified material, condition and competent assessment.
C. Workers, equipment and controls
| Item | Job-specific entry |
|---|---|
| Workers, training and specialist contractors | [ ] |
| Scrapers, sanders, extraction, brushes, rollers and spray equipment if permitted | [ ] |
| Substrate preparation, containment and clean-up equipment | [ ] |
| Access platforms, inspection, edge control and rescue | [ ] |
| Products, quantities, SDS and safe storage | [ ] |
| Ventilation, exposure controls and occupied-area separation | [ ] |
| Task-specific gloves, eye, clothing and respiratory protection | [ ] |
| Fire prevention for flammable products and waste | [ ] |
| Waste segregation, hazardous-waste decision and disposal route | [ ] |
HSE's COSHH assessment guide explains that the hazard may come from the product or the process, including dust generated by sanding. Identify how people could breathe in or contact the material, then control exposure; a safety data sheet by itself is not the job assessment. Lead and asbestos have separate regulations and need their own controls. An ordinary water-based paint may still need skin/eye protection and ventilation depending on product and task, while a specialist two-pack spray product can demand much more stringent controls. This template does not supply those controls by default.
Work at height should be planned around the actual surface and duration. HSE's height hierarchy begins with avoiding height where practicable, then preventing falls. Do not write “use ladder” for every ceiling or stairwell; check whether a platform, tower or other system is appropriate and how materials will be handled without overreaching. Segregate people below and keep the access route clear.
D. Work sequence and inspections
| Step | Describe the method | Control and evidence |
|---|---|---|
| 1. Brief and isolate work area | [Confirm scope, hazards, access, occupants and product.] | [Sign briefing; barriers/protection ready.] |
| 2. Inspect substrate | [Check old finish, damp, defects, services and specified preparation.] | [Release lead/asbestos/product hold points.] |
| 3. Protect and stage | [Cover floors/furniture, establish ventilation and safe storage.] | [Keep exits and other trades protected.] |
| 4. Remove/repair as approved | [State removal/repair system, tools and limits.] | [Specialist method if old hazardous coating/material.] |
| 5. Prepare surface | [Clean, fill, sand or abrade by assessed method.] | [Dust/extraction/skin controls; inspection.] |
| 6. Apply primer/coat | [Mix and apply to product instructions and specified conditions.] | [COSHH, ventilation, access and fire controls.] |
| 7. Allow cure/recoat | [State manufacturer interval and access restrictions.] | [No early reoccupation if hazard remains.] |
| 8. Inspect and correct | [Check coverage, finish, defects and any specification hold point.] | [Record approved rework and batch/area.] |
| 9. Clean and hand over | [Remove protection, manage waste, restore room.] | [Client acceptance, care/cure advice, defects.] |
The sequence should be tailored to the actual coating. A spray method is not a minor variant of brushing: overspray, ventilation, breathing protection, fire risk and environmental containment may change materially. Use a separate assessed specialist method if spraying is proposed. The same applies if stripping reveals lead paint or asbestos-containing material; stop affected work and obtain the appropriate competent plan.
E. Stop, change and emergency decisions
| Trigger | Immediate action and restart owner |
|---|---|
| Suspected lead/asbestos or unknown historic coating | [Stop disturbance; competent identification/assessment.] |
| Surface unexpectedly damp, unstable or contaminated | [Stop affected work; designer/client approves repair.] |
| Extraction/ventilation fails or vapour reaches occupants | [Stop; isolate and restore controls.] |
| Product substituted or SDS/application conditions differ | [Hold use; assess and approve alternative.] |
| Unsafe access or fall/overreach risk | [Stop; select and inspect better access.] |
| Fire/ignition concern, spill or uncontained waste | [Make safe, follow emergency/spill procedure.] |
| Unexpected damage to services or adjacent property | [Stop and report; competent repair and revised method.] |
Name who will change the document, communicate the revised method and confirm controls before restart. A worker should be able to stop on a suspect coating without feeling obliged to finish the room. Protect the evidence of what was found and avoid exposing occupants or other trades while seeking a decision.
F. Briefing and handover
| Person and role | Version briefed | Question/variation | Sign/date |
|---|---|---|---|
| [ ] | [ ] | [ ] | [ ] |
| [ ] | [ ] | [ ] | [ ] |
| [ ] | [ ] | [ ] | [ ] |
| Handover item | Evidence/owner |
|---|---|
| Product and colour/finish references | [ ] |
| Substrate repairs or unresolved defects | [ ] |
| Drying/cure and re-entry restrictions | [ ] |
| Ventilation, clean-up and waste completion | [ ] |
| Inspection/acceptance and maintenance advice | [ ] |
Do not re-open an occupied space simply because the coating feels dry. Follow product and exposure controls, and tell the client any access restriction. Handover should distinguish an accepted cosmetic finish from unresolved substrate or hazard work.
Example: repainting an occupied older office
The contractor is asked to redecorate a corridor in an older office. Before preparation, the supervisor reviews the building's materials information and old coating history. The team decides not to strip intact paint unnecessarily, but an area of damaged coating needs a competent lead assessment. That section is held while the rest of the work is planned. The corridor is divided into stages that preserve safe access and keep occupants away from sanding dust and wet product. A suitable platform is selected for the ceiling rather than overreaching from a ladder. Product SDS and ventilation requirements are briefed. When a hidden damp patch is uncovered, painting stops in that bay until the cause and repair are agreed. The finished area is inspected and opened only after the relevant product/access conditions are met. This is an example of decisions, not a ready-made method for the specific building.
Common method-statement failures
- Writing “sand existing paint” without identifying old coating hazards.
- Treating an SDS as the complete COSHH assessment.
- Applying a generic brush/roller method to a spray product.
- Relying on PPE without dust, vapour and occupant containment.
- Assuming a ladder is suitable for every surface or duration.
- Painting over damp, unstable or fire-relevant details without approval.
- Reopening a room with unresolved ventilation or curing restrictions.
- Signing off appearance without documenting substrate repair and residual defects.
The Complys RAMS page covers a project-specific method workflow; a generated document does not approve a paint system or specialist removal procedure. Software can organise a method; a competent person must inspect the surface, select controls and verify the work.