Home → Templates → Working in occupied premises risk assessment template
Templates

Working in occupied premises risk assessment template

Work in an occupied building needs a risk assessment that protects the people who remain there as well as the people doing the job. The useful starting point is a precise work area, the occupants and their normal routes, the activity and duration, and the practical boundary between the work and occupied space. Record who controls that boundary, what services or fire arrangements will change, how people will be told, and what makes the area safe to hand back. Copy the form below and adapt it with the building occupier before work starts.

This is a task-specific blank assessment for maintenance, installation or refurbishment in an occupied office, school, care setting, hospital, shop, residential common area or similar premises. It is not permission to work in every such setting. Some activities require a construction phase plan, permits, asbestos information, infection-control arrangements, fire-system isolation, safeguarding procedures or a specialist method statement. A completed form must identify those documents and their owners.

HSE's construction public-protection guidance says that work in schools and hospitals needs careful planning, with site access and vulnerable groups considered. HSE construction guidance also calls for clear agreement with the occupier on who maintains barriers and keeps uninvolved people away. The assessment therefore cannot simply say “keep public out” without showing how that will happen during normal opening hours, deliveries, breaks and emergencies.

Before filling the form: agree the work boundary

Walk the route with the occupier or their representative. Mark the work area, storage area, waste route, delivery point, emergency exits and adjacent occupied rooms. Ask whether the building will remain open during noisy, dusty, hot, high-level or service-isolation stages. If occupants cannot be effectively separated, change the sequence, time or location. Vacating part of a building may be the safer option; do not treat “out of hours” as automatically safe if cleaners, security staff or residents will still be present.

The client or occupier should provide reliable information about building hazards and operations. Ask for asbestos information before intrusive work, service drawings where relevant, fire and evacuation arrangements, known vulnerable users, access restrictions, infection-control requirements and any permit system. HSE asbestos guidance says that asbestos must be identified before maintenance or refurbishment that may disturb it; the person carrying out work should see relevant building records and assess whether further investigation is needed. An empty asbestos field is a stop point, not an invitation to assume none is present.

Copyable occupied-premises assessment

A. Job, people and agreement

FieldComplete for the actual premises
Building, floor, room and precise work boundary
Job description, work stages, dates and occupied hours
Contractor supervisor and competent assessor
Client/occupier contact and decision-maker
Occupant groups, including children, patients, residents, visitors or people needing assisted evacuation
Other contractors, cleaning/security staff and deliveries
Work-area plan, access route, storage and waste route
Relevant RAMS, permits, surveys, drawings and building rules
How changes and emergencies will be communicated
Approval, issue/version and review trigger

Write down who can stop the work if the agreed boundary or safe route fails. A named occupier contact matters because the contractor may not control building movements, alarms, doors or service shutdowns.

B. Segregation and occupied-building controls

DecisionSite-specific answer, owner and check
Can the work be moved to an unoccupied time or the occupants moved?
What physical barrier separates people from work, tools, dust and falling objects?
Who erects, inspects and maintains it, including during breaks?
How are entry points secured without obstructing escape?
Which pedestrian, wheelchair and delivery routes remain safe?
How are children or other vulnerable people prevented from entering?
What advance notice will occupants receive and in what format?
Who controls temporary changes to fire exits, alarms, doors or compartmentation?
What is the trigger for evacuation, suspension or area closure?
Who inspects, cleans and formally hands the area back?

A strip of warning tape may not be an adequate barrier for a live school corridor or public shop. Choose containment and access control for the actual hazard and people. Keep the boundary effective when workers are unloading, fetching materials or away from the task.

C. Hazard and action record

Work stage and hazardWho may be harmed and howExisting controls/evidenceAdditional action, owner and before-start hold point
Shared access: people, trolleys, deliveries and vehicles
Unauthorised entry or contact with tools, cables or openings
Dust, fumes, noise or vibration reaching occupied rooms
Asbestos, hidden services or unknown building fabric
Fire, hot work, alarm isolation or changed escape route
Electricity, water, gas, heating or ventilation isolation
Work at height and falling materials over occupied routes
Slips, trips, temporary lighting and accessible routes
Infection-control or clinical/care-setting requirements
Security, privacy, safeguarding or resident welfare
Waste, sharp items, chemicals and end-of-day housekeeping

For each row, separate a control already verified from an action still required. “PPE worn” does not control the exposure of a pupil, patient or visitor on the other side of a door. The assessment should identify the physical and organisational measure protecting them.

D. Building-system and emergency interface

QuestionRecord
Which alarms, detectors, sprinklers, doors or escape routes might be affected?
Who authorises and records any isolation or impairment?
What temporary protection or fire watch is required by the building procedure?
Which services must be isolated and proved safe before work?
How will occupants be informed of a planned interruption?
What happens if the work overruns or a service cannot be restored?
How do workers and occupants raise the alarm and evacuate?
First aid, emergency contacts and access for responders

Never isolate a fire system or block an escape route merely because a contractor's task would be easier. The occupier's fire arrangements and competent fire-safety decision must be reconciled with the work. If that cannot be done, change the work method or suspend the stage.

E. Stage release and handback

CheckPerson, time and evidence
Area and barrier inspected before occupants pass nearby
Permits, surveys and service information checked
Dust/noise/ventilation and occupant controls tested
Operatives briefed on routes, welfare and stop triggers
Daily end-of-shift clean and secure state confirmed
Services and fire provisions restored and verified
Waste removed, openings closed, temporary works removed
Occupier accepts the area back, with defects listed

If the job spans several days, use the handback check at the end of each day even if the work area remains closed. A partially complete area must remain protected from occupants and cleaners. Record a named person responsible for that condition.

How to make the assessment usable

1. Describe normal building life. A corridor that is quiet at 08:00 may become a school movement route, clinic queue or delivery route an hour later. Ask about peak periods, out-of-hours users and assisted evacuation. A risk assessment that covers only the contractor's immediate working hours is incomplete if the site is left partly altered overnight.

2. Sequence the highest-impact stages. Drilling, cutting, roof work, hot work and service shutdown may need different controls from setting up or decorating. Give each stage its own access and occupancy decision. If the work can be isolated to a vacant area, the benefit is both less exposure and simpler control.

3. Make the controls verifiable. Name the type and location of barrier; show the alternate route; identify who will test an isolation; state where dust extraction or containment will be used. “Inform occupants” should say who, when, through which channel and what information they need.

4. Link specialist assessments. An intrusive job needs asbestos and service information; hazardous substances may need a COSHH assessment; hot work may need a permit; a roof or MEWP task needs its own height and rescue plan. This occupied-premises form coordinates those controls. It does not replace them.

5. Define the stop condition. Stop if a barrier is breached, an unexpected occupant enters, a planned route closes, hidden material or service is found, ventilation fails, a fire alarm is impaired without agreed protection, or the scope changes. Reassess with the occupier before restart.

Example: replacing ceiling services in an open clinic

A contractor must access ceiling voids above a corridor used by patients and staff. The first proposal is to position a platform and work around people. The joint walk-through finds that the corridor is the accessible route to a treatment room and part of the evacuation route. The team moves the ceiling work to a planned closure period and agrees an accessible alternate route. The client supplies asbestos and service information for the ceiling zone. The contractor sets a physical boundary, controls dust and dropped materials, confirms which detectors might be affected and gets the building's fire-safety lead to agree any impairment procedure. At the end, they remove debris, reinstate the ceiling and services, check the fire provision and release the route with the occupier.

That example does not certify the ceiling void or prescribe a particular barrier. Those are site-specific decisions requiring competent information.

Who is responsible?

The contractor controls its work method, workers, equipment and work-area safeguards. The occupier or client controls information and decisions about building operations, occupants, access and systems. Their duties can overlap; record the interface instead of assuming the other party will handle it. Under the HSE public-protection guidance, site access and exclusion of unauthorised people need practical measures. A signed assessment is not proof that a barrier remained in place throughout the job.

Review the assessment when occupancy changes, a new group uses the area, a work stage moves, an alarm or service arrangement changes, a barrier fails, a new hazard is discovered, or an incident or complaint shows that controls did not work. Ask affected people whether the alternate route and communications are actually usable, especially in settings with vulnerable users.

Complys and the next step

Use this form as the site-specific assessment record. The Complys RAMS area is the relevant place to consider a job method statement, while risk assessment software describes storing and managing assessments. The software should not be presented as confirming asbestos status, approving fire-system isolation, choosing an infection-control method or securing an occupied boundary. Those decisions belong to competent people with current site information.

Next step: agree the occupied-building interface with the client, complete the form with named control owners, verify each pre-start hold point, brief the workforce and record handback before reopening the area.

Source, claim and writer-side QA register — checked 5 October 2026

Material claimPrimary sourceBoundary
Public and other workers must be protected; occupied schools and hospitals need careful planningHSE protecting the publicControls depend on the people and premises.
Agree responsibility for keeping uninvolved people away in occupied premisesHSE HSG150No universal barrier specification in this template.
Asbestos information must be considered before maintenance/refurbishment that may disturb itHSE construction asbestosCompetent survey/assessment may be required.
The occupied area may need to be vacated for some workHSE HSG151Site-specific decision; not a universal rule.

Cannibalisation: no exact live occupied-premises assessment form observed; this fillable interface form is distinct from generic risk assessment and RAMS explanation. Confirm repository, unpublished owners and proposed route. Product truth: links only to observed .co.uk pages and avoids claims of automated building-system or specialist approval. Jurisdiction: GB/HSE terminology; do not carry to Ireland. Links/CTA: RAMS and risk assessment software only, subject to current repo check. Writer-side QA: direct answer, usable staged form, vulnerable-user/public interface, asbestos and fire controls, stop/release gates, practical example, current primary sources. Independent whole-page and repo QA remain outstanding.