Higher-risk building (HRB) sounds like one definition. It isn't. The Building Safety Act runs two regimes โ one for buildings in occupation, one for buildings being designed and constructed โ and they define an HRB differently. Using the wrong one is the most common mistake, so this page keeps them apart.
An occupied building in England is a higher-risk building if it is at least 18 metres in height or has at least 7 storeys, and contains at least 2 residential units.
Legal duty โ Building Safety Act 2022, s65 ยท Measurement โ Higher-Risk Buildings (Descriptions and Supplementary Provisions) Regulations 2023 ยท BSR guidance, occupation-phase criteria
For a new building being designed or constructed, the threshold is the same โ at least 18 metres or at least 7 storeys โ but the qualifying uses are wider: a building with at least 2 residential units, or a care home, or a hospital.
Work to an existing building โ including changes of use or adding storeys โ has separate BSR guidance and additional building-definition considerations. This summary covers the new-building test; check the existing-building criteria separately.
Descriptions โ Higher-Risk Buildings (Descriptions and Supplementary Provisions) Regulations 2023 ยท Procedures โ Building (Higher-Risk Buildings Procedures) (England) Regulations 2023 ยท BSR guidance, design-and-construction criteria
| In occupation | Design & construction | |
|---|---|---|
| Height / storeys | โฅ18m or โฅ7 storeys | โฅ18m or โฅ7 storeys |
| Residential units | โฅ2 required | โฅ2, or a care home, or a hospital |
| Hospitals / care homes | Excluded | Included |
| Excluded uses | hospital, care home, secure residential, hotel, barracks | secure residential, hotel, barracks |
| Attached structures | may be independent sections | single building (cannot split) |
| Regime | BSA 2022 Part 4 | building-control regime (Gateways) |
Try the higher-risk building checker, read the accountable person's duties, or go back to Building Safety Act compliance.
Yes, but only in the design and construction regime. A care home meeting the height or storey threshold is a higher-risk building for design and construction. It is not a higher-risk building under the in-occupation regime, which is limited to buildings with at least 2 residential units.
Either one meets the height/storey limb: a building at least 18 metres tall or with at least 7 storeys qualifies on that limb. You still need the use limb as well (residential units, or โ in design and construction โ a care home or hospital).
No. Wales has its own separate regulations for higher-risk buildings. This page is about the England regime.